MBR Integrated Wastewater Treatment System: Intelligent PLC Control and Reusable Standard Effluent
MBR wastewater treatment system
,PLC-controlled wastewater treatment plant
,reusable effluent treatment system
An MBR integrated wastewater treatment system packs membrane bioreactor process into a transportable enclosure, replaces the secondary clarifier with membrane separation, and moves effluent quality from "compliant discharge" to "standard reuse water".
For water-scarce industrial sites, resorts and island projects, that difference is not a matter of a few indicator values: one investment covers both discharge compliance and water supply. The ZQ-MBR range from Zhongqiao Enlightenment covers 5 to 500 m³/day, ships with a programmable logic controller and remote communication module, and is designed to reuse-grade effluent.

The ceiling on conventional activated sludge effluent is set by gravity settling. Sludge and water separate by density difference in the clarifier, and effluent suspended solids stall at 20 to 30 mg/L; going lower requires filtration, a longer train and a larger footprint.
MBR changes the separation mechanism: submerged PVDF hollow-fibre membranes with pores in the 0.1 micrometre range hold back sludge, bacteria and most colloids, so effluent suspended solids stay below 10 mg/L and turbidity approaches 1 NTU.
Three consequences follow. First, the biological tank is no longer limited by sludge settleability, so mixed liquor can run at 8,000 to 12,000 mg/L — more biomass in the same volume, higher volumetric loading, smaller footprint. Second, sludge age extends beyond 20 days, giving nitrifiers time to establish, so ammonia removal stops depending on water temperature and loading luck.
Third, the clarifier and tertiary filtration disappear from the train, releasing the area they would have occupied.
|
Stage |
Main equipment |
Function |
|
Pre-treatment |
Basket or mechanical screen, equalization tank, lifting pumps |
Traps debris; balances flow and quality |
|
Biological |
Anoxic tank, aerobic tank, return systems, aeration |
Organic removal, nitrification and denitrification |
|
Membrane tank |
Modules, frames, scouring aeration, permeate pumps |
Solids separation; permeate drawn under controlled pressure |
|
Dosing and cleaning |
Sodium hypochlorite, citric or oxalic acid, cleaning pump |
Recovery cleaning and disinfection |
|
Disinfection |
UV or sodium hypochlorite |
Hygiene indicators for reuse |
|
Control |
PLC, HMI, level and pressure instruments, remote module |
Automatic operation and remote diagnosis |
Integration determines site workload. Hydrostatic testing and powered trial running are completed before dispatch; on site only four steps remain — levelling on the foundation, connecting inlet and outlet, bringing in power, and linked commissioning. For overseas projects this usually shapes the total schedule more than the equipment price does.
The value of automation is not moving switches onto a screen; it is writing experience-based judgement into logic. The ZQ-MBR control system runs four closed loops.
|
Loop |
Measured |
Actuated |
Logic |
|
Constant permeate flow |
Permeate flow, membrane tank level |
Permeate pump VFD |
Draws at set flow; ramps down at low level to protect membranes |
|
Aeration trimming |
Dissolved oxygen, blower current |
Blower VFD, valves |
Adjusts air to DO setpoint, balancing scouring and oxygenation |
|
Fouling monitoring |
Transmembrane pressure, temperature |
Backwash, maintenance clean |
Backwash at threshold; chemical clean if pressure keeps rising |
|
Return control |
Influent flow, ammonia |
Mixed liquor and sludge return pumps |
Separate return ratios set by C/N ratio |
Transmembrane pressure is the parameter worth watching. It turns membrane condition into a continuous reading: normal operation sits at 15 to 25 kPa, a slow rise means cake layer accumulation that online backwash can recover, and pressure that fails to fall after backwash means foulants have entered the pores and chemical cleaning is due.
Feed that curve into the remote platform and the operator can tell — without visiting — whether to backwash, clean, or investigate the influent.
The panel exposes a standard communication interface; connected to the cloud platform it provides cloud monitoring, analysis and management with live data and alarms on mobile. Unmanned operation really means fewer cases where someone must stand on site to decide: with level, blower current, transmembrane pressure and permeate flow transmitted, most anomalies can be characterised before dispatch.


|
Parameter |
Influent |
Effluent (reuse grade) |
Note |
|
COD (mg/L) |
≤500 |
≤50 |
Longer retention where biodegradability is poor |
|
BOD₅ (mg/L) |
≤350 |
≤10 |
Membrane retention removes particulate organics |
|
Ammonia (mg/L) |
≤45 |
≤5 |
Controlled at 8 below 12°C water temperature |
|
Suspended solids (mg/L) |
≤270 |
≤10 |
Typically stable below 5 in practice |
|
Total phosphorus (mg/L) |
≤5 |
≤0.5 |
Requires chemical phosphorus removal |
These values correspond to Chinese urban miscellaneous water quality standards for irrigation, toilet flushing and road washing. For landscape or cooling make-up, total dissolved solids and chloride need separate assessment, with reverse osmosis or softening added where required.
|
Model |
Capacity (m³/d) |
Dimensions (mm) |
Operating weight (t) |
Installed / running power (kW) |
Cost per m³ (CNY) |
Footprint (m²) |
|
MBR-0.5 |
10 |
3000×1000×2000 |
7.25 |
5.37 / 3.25 |
2.04 |
20 |
|
MBR-1.25 |
30 |
5000×1500×2000 |
17.24 |
7.27 / 4.25 |
0.92 |
27 |
|
MBR-3 |
70 |
6500×2250×2500 |
41.43 |
8.63 / 5.31 |
0.57 |
43 |
|
MBR-10 |
250 |
15500×3000×2700 |
138.63 |
26.07 / 15.27 |
0.51 |
102 |
|
MBR-12.5 |
300 |
9780×2930×2860 (two units) |
178.40 |
26.25 / 15.45 |
0.45 |
118 |
|
MBR-20 |
500 |
12200×3000×2860 (three units) |
292.60 |
38.90 / 23.10 |
0.42 |
165 |
Above 300 m³/day a single enclosure exceeds sensible transport and lifting limits, so the range switches to two or three parallel units. Parallel operation is not simple addition: each unit carries its own blower and permeate pump, rotating at low load so that scouring aeration stays continuous and large pumps avoid frequent starting at small flows.
Four project types fit this system. The first is the water-scarce plant: effluent reused for landscaping, toilet flushing, road washing and cooling make-up displaces mains water, and the saving offsets part of the operating cost. The second is resorts, hotels and commercial complexes, where land is tight and appearance matters — the unit can be buried or semi-buried with the surface restored to planting and walkways.
The third is islands, mining sites and construction camps overseas, where specialist operators are unavailable and remote diagnosis with unmanned operation becomes a requirement rather than a bonus. The fourth is upgrading an existing plant: converting the clarifier into a membrane tank lifts effluent from Grade B to Grade A without new footprint and without a shutdown.
Membranes are not a consumable; they are an asset. Three practices decide how long they actually last.
First, aeration is not negotiable. Membrane tank aeration does two jobs — supplying oxygen and creating a gas-liquid two-phase flow that scours the fibre surface. Trimming scouring air to save power looks harmless for a few weeks, then transmembrane pressure climbs faster, cleaning frequency doubles, and the electricity saving is returned with interest.
Second, chemical cleaning must be disciplined. Sodium hypochlorite removes organic fouling, citric acid removes inorganic scaling, and both concentration and soak time should follow the membrane manufacturer's values. Over-strength or over-long soaking damages fibres; rinsing must be thorough, because residual chemical inhibits the biological system.
Third, seasonal correction is required. Above 30°C, microbial activity and sludge production rise and fouling accelerates, so maintenance cleaning intervals shorten; below 12°C, nitrifier activity falls and retention time must extend or loading reduce. The control programme should offer a seasonal switching entry point rather than leaving it to site judgement.
On commissioned projects, modules last five to seven years under proper maintenance, and specific energy runs at 0.45 to 0.65 kWh per cubic metre excluding reuse pumping. Put both into whole-life cost and, at small flows, the gap between MBR and a conventional biology-plus-filtration-plus-disinfection train narrows considerably — while the advantages in footprint and effluent stability remain throughout.

Efficient and Stable Zhongqiao Box Integrated Sewage Treatment Equipment for domestic Wastewater treatment
Skid Mounted Integrated Containerized Sewage Treatment Plant Equipment MBR System For Municipal Industrial Use
Durability And Corrosion Resistance PP Material Sewage Water Treatment Plant Integrated